Versión en texto ¿Qué es?Dateas es un sitio independiente no afiliado a entidades gubernamentales. La fuente de los documentos PDF aquí publicados es la entidad gubernamental indicada en cada uno de ellos. Las versiones en texto son transcripciones no oficiales que realizamos para facilitar el acceso y la búsqueda de información, pero pueden contener errores o no estar completas.
Fuente: Federal Register
Federal Register / Vol. 86, No. 177 / Thursday, September 16, 2021 / Notices abutment that is equipped with a headgate and trashrack with 2-inch clear bar spacing; 4 a 26-foot-long, 22-footwide wood and steel powerhouse containing one 265-kilowatt vertical Flygt submersible turbine-generator unit; 5 a 400-foot-long, 20-foot-wide tailrace that discharges into the Cocheco River; 6 a generator lead, transformer, and transmission line that connect the project to the local utility distribution system; and 7 appurtenant facilities.
Watson Associates voluntarily operates the project in a run-of-river mode using an automatic pond level control system to regulate turbine operation, such that outflow from the project approximates inflow. The project creates an approximately 250foot-long and a 400-foot-long bifurcated bypassed reaches of the Cocheco River.
Downstream fish passage is provided by a bypass pipe located on the left side of the dam. There is no upstream fish passage facility at the project.
The current license requires a minimum flow release of 83 cubic feet per second cfs, or inflow to the impoundment, whichever is less from the dam to protect and enhance aquatic resources in the Cocheco River. The average annual generation of the project is approximately 1,100 megawatt-hours.
o. In addition to publishing the full text of this notice in the Federal Register, the Commission provides all interested persons an opportunity to view and/or print the contents of this notice, as well as other documents in the proceeding e.g., license application via the internet through the Commissions Home Page http
www.ferc.gov using the eLibrary link.
Enter the docket number excluding the last three digits in the docket number field to access the document P6240.
For assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-free, 866 2083676 or 202 502
8659 TTY.
You may also register online at https ferconline.ferc.gov/
FERCOnline.aspx to be notified via email of new filings and issuances related to this or other pending projects.
For assistance, contact FERC Online Support.
p. Procedural schedule: The application will be processed according to the following preliminary schedule.
Revisions to the schedule will be made as appropriate.
Issue Deficiency Letter if necessary October 2021
Request Additional Information October 2021
Issue Scoping Document 1 for comments January 2022
VerDate Sep<11>2014
16:44 Sep 15, 2021
Jkt 253001
Issue Acceptance Letter February 2022
Request Additional Information if necessary February 2022
Issue Scoping Document 2 March 2022
Issue Notice of Ready for Environmental Analysis March 2022
q. Final amendments to the application must be filed with the Commission no later than 30 days from the issuance date of the notice of ready for environmental analysis.
Dated: September 10, 2021.
Kimberly D. Bose, Secretary.
FR Doc. 202120003 Filed 91521; 8:45 am BILLING CODE 671701P
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission Docket No. CP2114000
Adelphia Gateway, LLC; Notice of Revised Schedule for Environmental Review of the Marcus Hook Electric Compression Project This notice identifies the Federal Energy Regulatory Commission staffs revised schedule for the completion of the environmental impact statement EIS for Adelphia Gateway, LLCs Marcus Hook Electric Compression Project. The Notice of Intent to Prepare an Environmental Impact Statement for the Proposed Marcus Hook Electric Compression Project and Schedule for Environmental Review, issued on May 27, 2021, identified September 10, 2021
as the final EIS issuance date. However, we are modifying this issuance date based on comments received on the draft EIS and based on Adelphia Gateway, LLCs supplemental information filed on August 25, 2021 to address comments.
Schedule for Environmental Review Issuance of the final EISOctober 1, 2021
90-day Federal Authorization Decision DeadlineDecember 30, 2021
If a schedule change becomes necessary, an additional notice will be provided so that the relevant agencies are kept informed of the projects progress.
Additional Information In order to receive notification of the issuance of the EIS and to keep track of all formal issuances and submittals in specific dockets, the Commission offers a free service called eSubscription. This can reduce the amount of time you spend researching proceedings by
PO 00000
Frm 00017
Fmt 4703
Sfmt 4703
51665
automatically providing you with notification of these filings, document summaries, and direct links to the documents. Go to https www.ferc.gov/
ferc-online/overview to register for eSubscription.
Additional information about the Project is available from the Commissions Office of External Affairs at 866 208FERC or on the FERC
website www.ferc.gov. Using the eLibrary link, select General Search from the eLibrary menu, enter the selected date range and Docket Number i.e., CP2114, and follow the instructions. For assistance with access to eLibrary, the helpline can be reached at 866 2083676, TTY 202 5028659, or at FERCOnlineSupport@ferc.gov. The eLibrary link on the FERC website also provides access to the texts of formal documents issued by the Commission, such as orders, notices, and rule makings. This notice is issued and published in accordance with 18 CFR
2.1.
Dated: September 10, 2021.
Kimberly D. Bose, Secretary.
FR Doc. 202120002 Filed 91521; 8:45 am BILLING CODE 671701P
ENVIRONMENTAL PROTECTION
AGENCY
EPAHQOW20200005; FRL761102
OW
Final National Pollutant Discharge Elimination System NPDES Pesticide General Permit for Point Source Discharges From the Application of Pesticides; Reissuance Environmental Protection Agency EPA.
ACTION: Notice of final permit issuance.
AGENCY:
This notice announces issuance by all 10 Environmental Protection Agency EPA Regions of the final 2021 National Pollutant Discharge Elimination System NPDES pesticide general permit PGPthe 2021 PGP.
The 2021 PGP, which has an effective date of October 31, 2021, replaces the existing permit 2016 PGP that expires at midnight on October 31, 2021, and authorizes certain point source discharges from the application of pesticides to waters of the United States in accordance with the terms and conditions described therein. EPA is issuing this permit for five 5 years in all areas of the country where EPA is the NPDES permitting authority.
DATES: The permit becomes effective on October 31, 2021, and will expire at SUMMARY: