Versión en texto ¿Qué es?Dateas es un sitio independiente no afiliado a entidades gubernamentales. La fuente de los documentos PDF aquí publicados es la entidad gubernamental indicada en cada uno de ellos. Las versiones en texto son transcripciones no oficiales que realizamos para facilitar el acceso y la búsqueda de información, pero pueden contener errores o no estar completas.

Fuente: Federal Register

50196

Federal Register / Vol. 86, No. 170 / Tuesday, September 7, 2021 / Notices
A notice of consideration of issuance of amendment to facility operating license or combined license, as applicable, proposed NSHC
determination, and opportunity for a hearing in connection with these actions, was published in the Federal Register as indicated in the safety evaluation for each amendment.
Unless otherwise indicated, the Commission has determined that these amendments satisfy the criteria for categorical exclusion in accordance
with 10 CFR 51.22. Therefore, pursuant to 10 CFR 51.22b, no environmental impact statement or environmental assessment need be prepared for these amendments. If the Commission has prepared an environmental assessment under the special circumstances provision in 10 CFR 51.22b and has made a determination based on that assessment, it is so indicated in the safety evaluation for the amendment.
For further details with respect to each action, see the amendment and
associated documents such as the Commissions letter and safety evaluation, which may be obtained using the ADAMS accession numbers indicated in the table below. The safety evaluation will provide the ADAMS
accession numbers for the application for amendment and the Federal Register citation for any environmental assessment. All of these items can be accessed as described in the Obtaining Information and Submitting Comments section of this document.

LICENSE AMENDMENT ISSUANCES
Arizona Public Service Company, et al; Palo Verde Nuclear Generating Station, Units 1, 2, and 3; Maricopa County, AZ
Docket Nos
Amendment Date
ADAMS Accession No
Amendment Nos
Brief Description of Amendments

Public Comments Received as to Proposed NSHC Yes/No.

50528, 50529, 50530.
August 17, 2021.
ML21225A093.
216, 216, 216.
The amendments revised the technical specifications TSs to adopt Technical Specifications Task Force TSTF Traveler TSTF501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control, Revision 1 ADAMS Accession Nos. ML090510686 and ML100850094, for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 Palo Verde.
The amendments revised Palo Verde TS 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air, by removing the current stored diesel fuel oil and lube oil numerical volume requirements from the TSs and placing them in the TS Bases so that they may be modified under licensee control. The TSs are also revised such that the stored diesel fuel oil and lube oil inventory would require that a 7-day supply be available for each diesel generator at Palo Verde. Corresponding surveillance requirements and TS Bases are also revised to reflect the above changes.
No.

Exelon FitzPatrick, LLC and Exelon Generation Company, LLC; James A FitzPatrick Nuclear Power Plant; Oswego County, NY
Docket Nos
Amendment Date
ADAMS Accession No
Amendment Nos
Brief Description of Amendments
Public Comments Received as to Proposed NSHC Yes/No.

50333.
August 9, 2021.
ML21131A127.
343.
The amendment revised the containment venting flow path as described in the FitzPatrick Technical Specification 3.6.1.3, Primary Containment Isolation Valves PCIVs, Surveillance Requirement 3.6.1.3.1.
No.

Exelon Generation Company, LLC; Clinton Power Station, Unit No. 1; DeWitt County, IL
Docket Nos
Amendment Date
ADAMS Accession No
Amendment Nos
Brief Description of Amendments

Public Comments Received as to Proposed NSHC Yes/No.

50461.
August 11, 2021.
ML21188A020.
239.
The amendment revised Technical Specification Section 5.5.13, Primary Containment Leakage Rate Testing Program, to allow a one-time extension to the 15-year frequency of the Clinton Power Station, Unit No. 1, containment integrated leakage rate test ILRT or Type A
test. The proposed one-time change would permit the current ILRT interval of 15 years to be extended by about 8 months.
No.

sradovich on DSKJLST7X2PROD with NOTICES

PSEG Nuclear LLC; Hope Creek Generating Station; Salem County, NJ
Docket Nos
Amendment Date
ADAMS Accession No
Amendment Nos
Brief Description of Amendments

VerDate Sep<11>2014

00:30 Sep 04, 2021

Jkt 253001

50354.
August 17, 2021.
ML21181A056.
229.
The amendment revised Technical Specification 2.1, SAFETY LIMITS, specifically, 2.1.1, THERMAL POWER, Low Pressure or Low Flow, and 2.1.2, THERMAL POWER, High Pressure and High Flow, to reduce the reactor vessel steam dome pressure value to address General Electric Nuclear Energy 10 CFR part 21 Safety Communication SC0503, 10 CFR part 21 Reportable Condition Notification: Potential to Exceed Low Pressure Technical Specification Safety Limit, issued on March 29, 2005, regarding the potential to violate the low pressure safety limit following a pressure regulator failure-open transient.

PO 00000

Frm 00185

Fmt 4703

Sfmt 4703

U:07SEN1.SGM

07SEN1

Acerca de esta edición

Federal Register - September 7, 2021

TítuloFederal Register

PaísEstados Unidos de América

Fecha07/09/2021

Nro. de páginas320

Nro. de ediciones7797

Primera edición14/03/1936

Ultima edición17/06/2026

Descargar esta edición

Otras ediciones

<<<Septiembre 2021>>>
DLMMJVS
1234
567891011
12131415161718
19202122232425
2627282930