Versión en texto ¿Qué es?Dateas es un sitio independiente no afiliado a entidades gubernamentales. La fuente de los documentos PDF aquí publicados es la entidad gubernamental indicada en cada uno de ellos. Las versiones en texto son transcripciones no oficiales que realizamos para facilitar el acceso y la búsqueda de información, pero pueden contener errores o no estar completas.
Fuente: Federal Register
50532
Federal Register / Vol. 86, No. 172 / Thursday, September 9, 2021 / Notices
Rayburn Dam, fit within the class of categorically excluded actions as listed in Appendix B to Subpart D of 10 CFR
part 1021, the Implementing Procedures and Guidelines of the National Environmental Policy Act of 1969, as amended 42 U.S.C. 43214347:
Categorical exclusions applicable to B4.3: Electric power marketing rate changes, which does not require preparation of either an environmental impact statement EIS or an environmental assessment EA. On May 27, 2021, Southwestern determined that categorical exclusion B4.3 applies to the current action.
Administrative Procedures Under the Administrative Procedure Act 5 U.S.C. 553d, publication or service of a substantive rule must be made not less than 30 days before its effective date, except 1 a substantive rule that grants or recognizes an exemption or relieves a restriction; 2
interpretative rules and statements of policy; or 3 as otherwise provided by the agency for good cause found and published with the rule. The Administrator finds good cause to waive the 30-day delay in the effective date of this action as unnecessary for the following reasons: 1 This is an extension of rates previously approved by FERC, pursuant to 10 CFR 903.23a;
2 there are no substantive changes, as the existing rate schedules and anticipated revenues remain the same;
and 3 the Administrator provided notice and opportunity for public comment more than 30 days prior to the effective date of the rate extension and received no comments.
Order In view of the foregoing, and pursuant to delegated authority from the Secretary of Energy, I hereby extend on an interim basis, for the period of two years, effective October 1, 2021, through September 30, 2023, the current Sam Rayburn Dam rate schedule:
Rate Schedule SRD15, Wholesale Rates for Hydro Power and Energy
lotter on DSK11XQN23PROD with NOTICES1
Signing Authority This document of the Department of Energy was signed on August 30, 2021, by Mike Wech, Administrator for Southwestern Power Administration, pursuant to delegated authority from the Secretary of Energy. That document, with the original signature and date, is maintained by DOE. For administrative purposes only, and in compliance with requirements of the Office of the Federal Register, the undersigned DOE Federal Register Liaison Officer has been
VerDate Sep<11>2014
19:38 Sep 08, 2021
Jkt 253001
authorized to sign and submit the document in electronic format for publication, as an official document of DOE. This administrative process in no way alters the legal effect of this document upon publication in the Federal Register.
Signed in Washington, DC, on September 2, 2021.
Treena V. Garrett, Federal Register Liaison Officer, U.S.
Department of Energy.
United States Department of Energy Southwestern Power Administration Rate Schedule SRD15 1
Wholesale Rates for Hydro Power and Energy Sold to Sam Rayburn Dam Electric Cooperative, Inc.
Contract No. DEPM7592SW00215
Effective During the period January 1, 2016, through September 30, 2023, in accordance with the Federal Energy Regulatory Commission FERC order issued in Docket No. EF162000 June 30, 2016, extension approved by the Assistant Secretary for Electricity in Rate Order No. 75 Sept. 22, 2019, and extension approved by the Administrator in Rate Order No. 78
August 30, 2021.
Applicable To the power and energy purchased by Sam Rayburn Dam Electric Cooperative, Inc. SRDEC from the Southwestern Power Administration Southwestern under the terms and conditions of the Power Sales Contract dated October 7, 1992, as amended, for the sale of all Hydro Power and Energy generated at the Sam Rayburn Dam and Reservoir.
Character and Conditions of Service Three-phase, alternating current, delivered at approximately 60 Hertz, at the nominal voltage, at the point of delivery, and in such quantities as are specified by contract.
1. Wholesale Rates, Terms, and Conditions for Hydro Power and Energy 1.1. This rate shall be applicable regardless of the quantity of Hydro Power and Energy available or delivered to SRDEC; provided, however, that if an Uncontrollable Force prevents utilization of both of the projects power generating units for an entire billing period, and if during such billing period 1 Supersedes
Rate Schedule SRD13.
Extended through September 30, 2023, by approval of Rate Order No. SWPA78 by the Administrator, Southwestern Power Administration.
PO 00000
Frm 00009
Fmt 4703
Sfmt 4703
water releases were being made which otherwise would have been used to generate Hydro Power and Energy, then Southwestern shall, upon request by SRDEC, suspend billing for subsequent billing periods, until such time as at least one of the projects generating units is again available.
1.2. The term Uncontrollable Force, as used herein, shall mean any force which is not within the control of the party affected, including, but not limited to, failure of water supply, failure of facilities, flood, earthquake, storm, lightning, fire, epidemic, riot, civil disturbance, labor disturbance, sabotage, war, acts of war, terrorist acts, or restraint by court of general jurisdiction, which by exercise of due diligence and foresight, such party could not reasonably have been expected to avoid.
1.3. Hydro Power Rates, Terms, and Conditions.
1.3.1. Monthly Charge for the Period of January 1, 2016, through September 30, 2023.
$380,316 per month $4,563,792 per year for Sam Rayburn Dam Hydro Power and Energy purchased by SRDEC
from January 1, 2016, through September 30, 2023.
FR Doc. 202119395 Filed 9821; 8:45 am BILLING CODE 645001P
DEPARTMENT OF ENERGY
Southwestern Power Administration Robert D. Willis Hydropower Project Rate Schedule Southwestern Power Administration, DOE.
ACTION: Notice of extension of Robert D.
Willis Hydropower Project rate schedule.
AGENCY:
The Administrator, Southwestern Power Administration Southwestern has approved and placed into effect on an interim basis Rate Order No. SWPA79, which extends the following existing Southwestern Robert D. Willis Hydropower Project rate: Rate Schedule RDW15, Wholesale Rates for Hydro Power and Energy. This is an interim rate action effective October 1, 2021, extending for a period of two years through September 30, 2023.
DATES: The effective period for the rate schedule specified in Rate Order No.
SWPA79 is October 1, 2021, through September 30, 2023.
FOR FURTHER INFORMATION CONTACT: Ms.
Fritha Ohlson, Senior Vice President and Chief Operating Officer, Office of SUMMARY: